Sign in

Aurora City Council passes one-year moratorium pausing new data centers

Add On the record as a preferred source on Google
Aurora City Council passes one-year moratorium pausing new data centers
Photo: North Denver News

Key facts

  • The Aurora City Council unanimously approved a one-year moratorium on new data centers Nov. 23, 2026.1
  • Vantage Data Centers abandoned its proposed Trident campus on East 48th Avenue the same day the council approved the moratorium.1
  • The council unanimously advanced an ordinance Nov. 23 that would prohibit future sales and use tax incentives for data centers.1

Aurora City Council unanimously approved a one-year moratorium on new data centers Nov. 23, 2026, covering municipal territory west and south of Interstate 70 and Powhaton Road.1

The pause, effective through Sept. 30, 2027, follows months of community opposition and exempts previously accepted applications, officials said.1

Vantage Abandons Trident Campus

Vantage Data Centers abandoned its proposed Trident campus on East 48th Avenue the same day the council approved the moratorium, City Attorney Peter Schulte announced during the Nov. 23 meeting, drawing applause from residents.1

The proposed campus was to be built on 108 acres near the northwest corner of E-470 and East 48th Avenue..1 Vantage submitted its initial development application in August 2025 and had completed four rounds of municipal reviews before withdrawing, officials said.1

Vantage Vice President of North American Public Policy Misty Allen said the company voluntarily initiated a review of alternative sites in response to community concerns.1

A City of Aurora spokesperson said neither City Manager Jason Batchelor, Schulte nor other city team members were aware of the abandonment until it was reported near the start of the meeting.1

Community Opposition

Approximately 100 residents gathered Sept. 22 to discuss the proposed Trident development, including homeowners from The Reserve, a Green Valley Ranch community for adults aged 55 and older..1 Attendees raised concerns about property values, utility consumption, noise and potential environmental effects.1

More than 50 people registered to speak in support of development restrictions at the council’s Oct. 26 meeting..1 Residents argued facilities like Trident would bring noise and pollution.1

The original Trident campus design included approximately 334 megawatts of computing capacity and an estimated total demand of 500 megawatts..1 The proposal estimated approximately 800,000 gallons of water would be needed to fill 10 chiller units initially, with closed-loop cooling equipment used afterward.1

Council Vote And Exemptions

The council unanimously advanced an ordinance Nov. 23 that would prohibit future sales and use tax incentives for data centers, requiring another formal vote and preserving existing agreements..1 Aurora previously committed to four incentive agreements with a combined maximum value of approximately $83 million, with the Trident arrangement accounting for up to $39 million in potential tax rebates.1

The council approved a prohibition on water-intensive evaporative cooling Sept. 28, with previously accepted applications exempt..1 The Planning and Zoning Commission approved recommended code changes Nov. 10, including a minimum buffer of 750 feet between new data centers and residentially zoned areas and a requirement for noise studies.1

Mayor Mike Coffman supported excluding areas farther from established neighborhoods to preserve industrial investment opportunities.1

Councilmember Curtis Gardner was absent from the meeting..1 The council had previously rejected a proposed six-month pause on Aug. 10, with Coffman casting the deciding vote against it.1 A motion to reconsider an indefinite moratorium failed Oct. 26, receiving six of the required seven votes.1

Councilmember Stephanie Hancock supported the latest moratorium after opposing earlier proposals, emphasizing neighborhood safety and efficient construction..1 Chaz Tedesco, representing a local labor union, opposed the pause, emphasizing employment opportunities for construction workers.1

Sources

Every number in the story points here. Each links to the original reporting.

Who reported it 1 outlet
LeftCenterRight

CenterNorth Denver News

    See a sentence its source doesn’t back up?

    Tell us the source number and what’s wrong. We check every report. If we change the story, the fix goes on the corrections page with the old wording.

    More like this