CJI Surya Kant recuses himself from hearing plea related to Supertech projects

·

CJI Surya Kant recuses himself from hearing plea related to Supertech projects
Photo: The Hindu

Key facts

  • The top court had restrained all the tribunals and High Courts from passing any order that could lead.1
  • The apex court exercised its extraordinary power under Article 142 of the Constitution to uphold the December 12.1
  • The court had last heard the matter on October 27.2

Chief Justice of India Surya Kant recused himself from hearing a plea related to Supertech insolvency and homebuyers' dispute on Monday, November 23, 2026.1

One of the applicants was personally known to Surya Kant.1

The CJI said he will constitute a special bench to hear the matter.1

The bench comprising the CJI and Justices Joymalya Bagchi and V. Mohana reserved its order in the matter on November 16.1

NBCC Tasked With 16 Stalled Projects

State-owned NBCC was tasked with completing 16 stalled housing projects of debt-ridden realty firm Supertech.1

NBCC told the top court that it would like to exit if the homebuyers did not want its involvement.1

Earlier, the apex court on February 5 upheld a National Company Law Appellate Tribunal (NCLAT) order asking NBCC to complete 16 housing projects of Supertech Limited.1

The top court had observed that its concern was about the homebuyers and also about who would execute these projects.1

The top court had earlier come to the rescue of thousands of hassled homebuyers waiting for the delivery of their houses for almost two decades.1

The top court had restrained all the tribunals and High Courts from passing any order that could lead to the stalling of the construction work to be completed by NBCC Limited.1

The apex court exercised its extraordinary power under Article 142 of the Constitution to uphold the December 12, 2024 order of the NCLAT, asking the NBCC to take over the projects in the interest of homebuyers.1

The bench noted that Supertech, according to many homebuyers, had booked around 51,000 houses for delivery during 2010-12.1

The bench directed the NBCC to undertake the projects and complete those expeditiously as envisaged by an expert committee set up by the NCLAT.1

The NCLAT, on December 12, 2024, asked the NBCC to complete the 16 projects, comprising 49,748 homes in Uttar Pradesh, Uttarakhand, Haryana and Karnataka.1

Around 27,000 homebuyers await receiving houses in these projects.1

The NCLAT judgment came after the October 1, 2014 order of the top court that allowed the insolvency appellate tribunal to examine and decide a proposal of the NBCC seeking to complete the stalled projects.1

The construction work for the 16 projects would start on May 1, 2025.1

The NBCC had sought to complete the projects, launched in the National Capital Region (NCR), Dehradun and Bengaluru.1

The completion of the residential units took a hit owing to a financial crisis faced by the realty major, leading to insolvency proceedings beginning in 2021.1

The NBCC had submitted the terms of reference for undertaking the pending projects of Supertech before the NCLAT.1

The public sector unit (PSU) had proposed to complete the 16 projects in three phases.1

Under Phase 1, the NBCC had proposed to complete Eco-Village-2 (Greater Noida), Romano (Noida), Capetown (Noida), Czar Suites (Greater Noida), Eco-village-3 (Greater Noida), Sports Village (Greater Noida) and Eco-citi (Noida).1

Under Phase 2, the NBCC had proposed to undertake Northeye (Noida), Upcountry (Yamuna Expressway), Eco-village-1 (Greater Noida), Meerut Sports City (Meerut) and Green Village (Meerut).1

For Phase 3, the NBCC had proposed to undertake Hilltown (Gurugram), Aravile (Gurugram), Rivercrest (Rudrapur), Doon Square (Dehradun) and Micasa (Bengaluru).1

Court Takes Up Amicus Curiae Application

The court had last heard the matter on October 27, when it took up an application filed by amicus curiae and advocate Rajiv Jain, who sought the appointment of a court-monitored committee to oversee the completion of the 16 projects.2

NBCC has also faced criticism from homebuyers, who pointed out that more than ₹30 crore had been spent on hiring the company since it was appointed project management consultant (PMC) for the 16 Supertech projects by the National Company Law Appellate Tribunal (NCLAT) in December 2024, without a single tender being issued.2

The court said that homebuyers would not be burdened further, pointing to unsold inventory and vacant plots within the projects as potential sources of funds to complete the stalled construction work.2

In May, the NCLAT refused to grant the exemption and rejected NBCC’s plea for enhanced fees on the sale of unfinished flats in the 16 projects.2

Report an error in this story

Sources

The numbers in the story point here. Each one links to the original article.

    See a sentence its source doesn’t back up?

    Tell us the source number and what’s wrong. We check every report. If we change the story, the fix goes on the corrections page with the old wording.