Key facts
- The FEMA award includes funding for the restoration of the surrounding area.1
- The project cost is estimated to be around $28 million, and the county anticipates the remaining 25% of the cost will be covered by the state.2
- County Administrator Josh Milow said FEMA’s share covers about 75% of the project cost.2
The Federal Emergency Management Agency has awarded Blue Earth County over $21 million for the Rapidan Dam removal project.2
The funding is for the removal of the Rapidan Dam and restoration of the surrounding area.1
The award was approved after severe storms and floods in June 2024 damaged public infrastructure.3
Project Cost And State Share
County Administrator Josh Milow said FEMA’s share covers about 75% of the project cost, which is estimated to be around $28 million.2
Milow said the county is excited to be at this point in the project.2
The June 2024 partial failure of the dam was almost two and a half years ago.2
The funding covers the dam removal portion of the project, and is not for the County Road 9 replacement project.2
The County Road 9 project came from the Federal Highway Administration.2
The county is still working with their consulting engineer on design elements for the dam removal and restoration of the west bank.2
The County Road 9 project began a couple of weeks ago, with the county hoping to finish that project in the fall of 2028.2
FEMA Award Details
FEMA announced Monday that it approved more than $21 million for the county’s public works department to remove the Rapidan Dam and restore the surrounding area after severe storms and floods in June 2024 damaged public infrastructure.3
During the 2024 severe weather event, the dam partially failed and was overtopped.3
FEMA said that led to a new channel around the west abutment and the loss of surrounding land and property.3
The award will support a locally developed plan to demolish the dam and restore both banks of the Blue Earth River at the dam site, according to FEMA.1