Key facts
- Anthropic has failed to obtain federal air permits for over 50 natural gas turbines installed in neighboring communities in Mississippi.1
- The application faces a delay request from Arizona Attorney General Kris Mayes.2
- Colossus 3, if approved, would also rely on gas turbines until Arizona Electric Power Cooperative.1
SpaceX has named and shared a construction timeline for a proposed mega data center campus in Cochise County, prior to any local vote.1
The company said the supercomputing facilities will rank among the world’s most advanced AI training clusters.2
SpaceX CEO Elon Musk announced on social media that the data center would be named Colossus 3.1
Colossus 1 and 2 are two other mega data centers SpaceX already operates in Tennessee.1
The campuses run on thousands of Nvidia AI chips.1
The campuses are powering a super computer SpaceX refers to as Colossus.1
The computer’s original purpose was to train Grok, an AI assistant built by xAI.1
Colossus 1 is currently leased to another AI company, Anthropic, to train its model, Claude.1
Anthropic has failed to obtain federal air permits for over 50 natural gas turbines installed in neighboring communities in Mississippi to power those centers, per a Reuters investigation.1
Scientific American reports Mississippi officials made an exception for SpaceX to operate the turbines for a year without permits.1
The NAACP is suing on behalf of residents who say they’ve been flooded with harmful noise and emissions.1
Arizona attorney general seeks delay
Arizona Attorney General Kris Mayes called for a delay on a vote on the project.2
In her letter, Mayes cited concerns about water, power, noise and the environment.2
Mayes argued there were too many unknowns for the commission to approve a special use permit.2
Late last week, Mayes' office asked the county Planning and Zoning Commission to delay a vote on the project.2
In the draft letter, county staff questioned Mayes' authority to request a delay on the vote.2
The letter asks whether the effort is about reaching an informed decision or about personal political gain.2
Staff wrote they are disappointed Mayes did not contact them directly.2
Staff wrote they do not understand why she is holding a town hall in the county Dec. 3.2
The Cochise County Board of Supervisors directed staff to write a response letter to Mayes.2
What the project would bring
The site is planned a few miles from the community of Cochise and Willcox Playa, where thousands of sandhill cranes, a federally protected bird, migrate each year.1
Colossus 3, if approved, would also rely on gas turbines until Arizona Electric Power Cooperative, the utility that serves that part of the state, could generate the 6 gigawatts SpaceX has requested.1
That’s enough energy to power 4.5 million homes, a million more than there are in Arizona.1
The company said it has followed the county’s established process and engaged with residents and local officials.2
SpaceX said it would pay for $3.6 billion in grid upgrades and use treated wastewater.2
SpaceX said the project would bring 1,000 jobs to the community.2
A professor’s take on the push
Ken Gillingham, a professor of economics at Yale University who researches data centers, said SpaceX has a questionable track record in this area.2
Gillingham said SpaceX is known to be using diesel generators in populated areas.2
Gillingham said companies are competing to build advanced AI.2
Gillingham said companies look for places with a lot of flat, inexpensive land, that’s near electricity transmission, that’s near power plants, where local officials are likely to be more accommodating.2
Gillingham said a large number of Americans have a deep, deep distrust of data centers.2
What’s next
Cochise County zoning and planning commissioners are planning to vote on the company’s application on Dec. 9.1
If it receives a majority vote, it can move forward without board approval, unless county supervisors decide to appeal in accordance with local regulations.1
Energy service agreements with AEPCO and the intended retail electric service provider, Sulphur Springs Valley Electric Cooperative, will need approval from the Arizona Corporation Commission, the state’s utility regulator.1
State environmental, water and geological agencies must also review and approve aspects of the application.1
Sources
Every number in the story points here. Each links to the original reporting.
LeftKJZZ
CenterAZFamily
See a sentence its source doesn’t back up?
Tell us the source number and what’s wrong. We check every report. If we change the story, the fix goes on the corrections page with the old wording.