Key facts
- Michigan Gov. Gretchen Whitmer announced Tuesday she was putting environmental permit considerations for the Enbridge’s Line 5 tunnel project.1
- The state Supreme Court over the summer raised legal questions over the Line 5 tunnel project, and at the end of July ordered the Michigan Public Service Commission to revisit its decision to issue a permit for the project.1
- Pipeline opponents filed two separate requests for a contested case on a set of permits EGLE approved in July.1
Michigan Gov. Gretchen Whitmer announced Tuesday that she has directed the Michigan Department of Environment, Great Lakes and Enbridge Energy to suspend further action on permits connected to the proposed Great Lakes Tunnel Project, known as Line 5.4
The state considers legal questions raised by a recent court ruling.4
Whitmer said in a statement that her ultimate goal is to get Line 5 out of the water.4
What the permits cover
The 645-mile pipeline runs from northwest Wisconsin to southwest Ontario, and includes a 4.5-mile dual segment resting on the bed of the Straits of Mackinac, where Lake Michigan and Lake Huron meet.1
The Michigan Department of Environment, Great Lakes, and Energy issued permits in July 2026 and previously in 2021.1
Both permitting rounds included detailed technical reviews, public meetings, hearings, and consideration of thousands of public comments.1
The permitting rounds involved extensive interaction between Michigan’s tribal leaders and state agencies.1
Court orders commission to revisit permit
At the end of July, the Michigan Supreme Court ordered the Michigan Public Service Commission to revisit its decision to issue a permit for the project.1
The court ruled that the commission, which regulates Michigan’s energy and utility companies, had not properly considered the environmental harms that could arise from extending the lifespan of the oil pipeline.1
Opponents file contested case requests
Following Whitmer’s announcement, pipeline opponents filed two separate requests for a contested case on a set of permits EGLE approved in July, arguing that the tunnel project posed a serious threat to the environment and the lifeways and cultural resources of Native American tribes in the region.1
The fight against Line 5 has stretched on for years, with tribal nations and environmental advocates calling for the pipeline to be shut down.1
EGLE suspends further action
EGLE Strategic Communications Advisor Scott Dean confirmed the department was suspending further permitting action until the legal questions are resolved.1
“Taking a step back until we have greater clarity is the right thing to do for the Great Lakes, our natural resources, and the communities whose livelihoods depend on them,” Dean said.
Enbridge responds to court decision
Enbridge spokesperson Ryan Duffy said the Michigan Supreme Court’s decision to revoke the permit from the public service commission had introduced new uncertainty as the company aims to secure the permits needed to move forward with the tunnel.1
“The Michigan Department of Environment, Great Lakes, and Energy issued permits in July 2026 and previously in 2021. Both permitting rounds included detailed technical reviews, public meetings, hearings, and consideration of thousands of public comments,” Duffy said. “They also involved extensive interaction between Michigan’s tribal leaders and state agencies.”
Bay Mills Indian Community president weighs in
Whitney Gravelle, president of the Bay Mills Indian Community, said the decision is not the finish line.1
“This decision is not the finish line,” Gravelle said.
Timeline of the permit process
The Michigan Supreme Court issued its decision, In re Application of Enbridge Energy to Replace and Relocate Line 5, which concerned a separate permit issued by the Michigan Public Service Commission in 2023 for the same proposed tunnel beneath the Straits of Mackinac.2
The court found that the MPSC’s review should have included certain environmental harms, vacated the permit the Commission had issued to Enbridge, and remanded the matter back to the MPSC to reconsider the permit application in light of the Court’s decision.3
The release says Whitmer’s announcement acknowledges the time it will take for Enbridge to seek a permit again from the MPSC after the delay and uncertainty the court’s decision introduced.2