- The proposed SpaceX data center in Cochise County doesn’t pose a risk to Arizona’s electric power supply or to the Willcox Basin’s fragile groundwater supply, the company said.1
- Attorney General Kris Mayes asked the panel to delay its vote on the $50 billion data center project because of what she sees as its potential to cause major impacts to both water and power supplies.1
- SpaceX official Sheila McCorkle wrote to the commission that the company has followed established county procedures in pursuing its application.1
The proposed SpaceX data center in Cochise County doesn’t pose a risk to Arizona’s electric power supply or to the Willcox Basin’s fragile groundwater supply, the company said, pushing back against allegations to that effect from Attorney General Kris Mayes.1
Because of those and other reasons, the Cochise County Planning and Zoning Commission shouldn’t grant Mayes' request to delay its planned Dec. 9 discussion of the company’s proposal, a top SpaceX official said in a letter to the commission.1
Mayes' Concerns
Attorney General Kris Mayes issued a warning in a letter to the Cochise County Planning and Zoning Commission..2 On Nov. 19, she wrote that the proposed center will require close to 20% of Arizona’s total current electric generating capacity and could have major effects on overall energy reliability in the state.2
Mayes asked the panel to delay its vote until other state and federal agencies weigh in on the $50 billion data center project because of what she sees as its potential to cause major impacts to both water and power supplies.1
Besides water and power supplies, Mayes' letter raised concerns about the data center’s effects on traffic from vehicles using or serving the center, its possible interference with activities by Fort Huachuca on the neighboring Willcox Playa, and fire risks from major battery storage facilities that would be part of the center.1
SpaceX’s Response
On Nov. 24, SpaceX official Sheila McCorkle wrote to the commission that the company has followed established county procedures in pursuing its application, “engaged with residents and local officials and put the entire proposed campus before the commission in one application.”1
McCorkle is a vice president for SpaceX.1
“The commission should decide this case on what SpaceX has proposed, and on the commitments we’re prepared to make enforceable conditions, not on assumptions described in the attorney general’s letter about facilities that aren’t part of this application,” McCorkle wrote.
The commission has the full application before it, residents have a hearing on the calendar, and the agencies responsible for later approvals have their own proceedings, McCorkle wrote.1
Energy Supply Details
The proposed campus would receive its operating power from the grid, SpaceX said.1
The company noted that Mayes used the fact that the Apache Generating Station in Benson uses 625 megawatts of power to question whether the power plant has capacity to serve the center’s first 1,500 megawatts of power, let alone the 6,000 needed to serve the center at its full capacity.1
The company said Apache Station’s generating capacity won’t directly serve the SpaceX center.1
Instead, SpaceX will work with the station’s owner, the Arizona Electric Power Cooperative, to obtain wholesale power from across the Western electric grid.1
The power company, also known as AEPCO, will deliver that regional power through its transmission system to the Sulphur Springs Valley Electric Cooperative to provide retail service to the data center, SpaceX said.1
A proposed agreement which the company and the two cooperatives are negotiating calls for SpaceX to pay for its electricity and related service costs, prepare for network upgrades required to serve the data center campus, and post some kind of financial...1
One key fact not spelled out in SpaceX’s letter to Mayes is how much of its energy supply would come from renewable sources such as solar and wind energy and how much would come from fossil fuels such as oil and natural gas.1
McCorkle’s letter criticizes Mayes for raising concerns about facilities to provide power to the center that SpaceX hasn’t proposed, including building a new natural gas power plant at the site.1
The data center would hold up to nine computing buildings, all nearly 40 feet tall, and require six gigawatts of power when fully built and operating.1
Sources
Every number in the story points here. Each links to the original reporting.